Update on CR30A Western Lake Pedestrian Bridge The boardwalk on the western end of the project has been framed and decked. The concrete piles and pile caps are in place. The path between the two bridges has been constructed and sod installed. Both timber and concrete piles are being driven for eastern boardwalk and bridge. Daily lane closures are still in effect. A total closing of CR30A is being scheduled in order to set the bridge spans. The dates will be announced as soon as the schedule is confirmed. At your service, Louis E. Svehla Public Information Manager Walton Board of County Commissioners